What cycle time would match capacity and demand if demand is 120 units a day, there are two
shifts of 480 minutes each, and workers are given three half-hour breaks during each shift, one of
which is for lunch or dinner?
. Compute the takt time for a service system that intended to perform a standardized service.
The
system will have a total work time of 440 minutes per day, two 10-minute breaks, and an hour for
lunch. The service system must process 90 jobs a day.