In month 9 the following project information is available: actual cost is $2,000, earned

value is $2,100, and planned cost is $2,400. Compute the SV and CV for the project.

 

. On day 51 a project has an earned value of $600, an actual cost of $650, and a planned

cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of

the project on day 51?