Omega 2 Project. Using the “complexity weighting” scheme shown in Table

5.2 and the following function point complexity weight table, estimate the

total function point count. Assume historical data suggest five function points equal

one person a month and six people have been assigned to work on the project.

Complexity Weight Table

Number of inputs 15 Rated complexity low

Number of outputs 20 Rated complexity average

Number of inquiries 10 Rated complexity average

Number of files 30 Rated complexity average

Number of interfaces 50 Rated complexity high

a. What is the estimated project duration?

b. If 20 people are available for the project, what is the estimated project duration?

c. If the project must be completed in six months, how many people will be needed for

the project?