Which of the following processes involves determining the policies, procedures, and

documentation that will be used for planning, executing, and controlling the project

schedule?

.  Planning schedule management

.  Defining activities

.  Estimating activity resources

  Activity sequencing

 Predecessors, successors, logical relationships, leads and lags, resource requirements,

constraints, imposed dates, and assumptions are all examples of .

  items in an activity list

.  items on a Gantt chart

  milestone attributes

  activity attributes